Last minute finishing work is progressing well. The drywall guys were working this morning to patch up the wall in the linen closet which we had ripped open on Monday to run a water line to the attic (in case we want a humidifier attached to the furnace there). Yesterday a carpenter and the plumber reconfigured the locations for the hot water heaters because the kind that mount in the wall aren’t made any longer. The exterior wall had to be patched up and siding applied. The painter even came to finish it off so that the plumber could install the water heaters (possibly today).

We had someone come and install the dishwasher that the plumber was having trouble with:

And the carpet is now complete in the basement and the second floor. Here’s the view from our bedroom out into the hallway and master bath: